Scheduled
Dear customer,

We would like to inform you of an emergency maintenance activity at our gb-bournemouth-1 data centre. Please find details of this maintenance below:

Start date: 20/09/2024 11:00 AM BST/10:00 UTC
End date: 20/09/2024 12:00 AM BST/11:00 UTC

Affected data centre: gb-bournemouth-1

Event Type: Network hardware replacement

Description: Further to the outage during 2024-09-17, we are replacing a faulty switch to restore resilient connectivity in our gb-bournemouth-1 datacentre.

Client Impact: At-risk, possible service interruption. We do not anticipate prolonged service interruptions, but there is a possibility of a momentary interruption as network traffic switches to the resilient setup.

Action required: We advise all users to ensure a backup of their virtual machines and data is taken prior to the maintenance window and on a regular basis.