Main electrical entrance maintenance in ca-montreal-3
Scheduled for Oct 2, 10:00 - 18:00 UTC
Scheduled
Dear customers,

We would like to inform you of a planned maintenance activity at our ca-montreal-3 data centre. Please find details of this maintenance below:

Start date: 02/10/2024 11:00 AM BST/10:00 UTC
End date: 02/10/2024 19:00 PM BST/18:00 UTC

Affected data centre: ca-montreal-3

Event Type: Main Electrical Entrance maintenance

Description: The purpose of this maintenance is to ensure the connection remains reliable and aligns with industry standards.

Risk: Low. We don’t anticipate downtime during this maintenance window, as operations will switch to the backup generators.

Impact: Low.

Action required: We advise all users to ensure a backup of their virtual machines and data is taken prior to the maintenance window and on a regular basis.

If you have questions or concerns about the maintenance activity, please contact our support team.
Posted Sep 04, 2024 - 16:06 UTC
This scheduled maintenance affects: Data centres (ca-montreal-3).