Planned Infrastructure Upgrades
Scheduled Maintenance Report for Cudo Compute
Completed
The scheduled maintenance has been completed.
Posted Feb 29, 2024 - 13:00 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 29, 2024 - 11:00 UTC
Scheduled
Dear customers,

We would like to inform you of a planned maintenance activity at our us-santaclara-1 data centre. Please find details of this maintenance below:

Start date: 29/02/2024 11:00 AM GMT/11:00 UTC
End date: 29/02/2024 1:00 PM GMT/13:00 UTC

Affected data centre: us-santaclara-1

Event Type: Storage Infrastructure Upgrades

Description: Our Infrastructure team will be performing software upgrades to the locations storage infrastructure within the maintenance window. These works are required in preparation for the roll-out of new storage functionality.

Risk: The activity is expected to be non-disruptive to our core service, however, due to the nature of the works, we are classifying this period as 'at risk'.

Impact: Low. Some users may notice reduced storage performance during the works.

Action required: We advise all users to ensure a backup of their virtual machines and data is taken prior to the maintenance window and on a regular basis.
Posted Feb 13, 2024 - 14:33 UTC
This scheduled maintenance affected: Data centres (us-santaclara-1).