Planned maintenance - us-newyork-1 - host storage software upgrade - 18/03/2025

Scheduled Maintenance Report for Cudo Compute

Completed

The scheduled maintenance has been completed.
Posted Mar 18, 2025 - 15:30 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 18, 2025 - 13:30 UTC

Scheduled

Dear customers,

We would like to inform you of a planned maintenance activity at our us-newyork-1 data centre. Please find details of this maintenance below:

Start date: 18/03/2025 1:30 PM GMT/13:30 UTC
End date: 18/03/2025 3:30 PM GMT/15:30 UTC

Affected data centre: us-newyork-1

Event Type: Host storage software upgrades

Description: Our Infrastructure team will be performing software upgrades to the storage infrastructure within the maintenance window.

Risk: The activity is expected to be non-disruptive to our core service, however, due to the nature of the works, we are classifying this period as 'at risk'.

Impact: Low. End user operations will continue as normal during the maintenance window and after.

Action required: We advise all users to ensure a backup of their virtual machines and data is taken prior to the maintenance window and on a regular basis.

We appreciate your understanding. If you have issues of concerns regarding the activity, please contact our support team by registering a support ticket or by email at support@cudocompute.com.
Posted Mar 12, 2025 - 16:03 UTC
This scheduled maintenance affected: Data centres (us-newyork-1).